Specification on handover technical documentation for petrochemical construction projects
1 Scope
This standard specifies the requirements of the technical documentations for the completion of petrochemical construction projects, such as design, procurement, construction, inspection, etc., which are formed during the process from project commencement to project completion and acceptance.
This standard is applicable to the preparation, sorting and delivery of handover technical documentations for newly constructed, extended and renovated petrochemical projects.
2 Normative references
The following referenced documents are indispensable for the application of this standard. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
GB/T 10609.3 Technical drawings—Folding on documents
GB/T 11822 General requirements for the file formation of scientific and technological archives
GB/T 14689 Technical drawings—Size and layout of drawing sheets
GB 50300 Unified standard for constructional quality acceptance of building engineering
GB/T 50328 Code for putting construction project documents into records
DA/T 28 Requirements for filing of records and archival arrangement of national construction of key project
SH/T 3508 Unification criterion of construction quality check and acceptance for petrochemical engineering project installation
SH/T 3903 Project supervision specification on petrochemical construction work
SH/T 3904 Regulation for acceptance of completed construction projects in petrochemical industry
3 Terms and definitions
For the purposes of this standard, the terms and definitions given in GB/T 50328, SH/T 3903 and SH/T 3904 apply.
3.1
handover technical documentation
general designation of technical documentations, such as the project realization process, evidence that the use function meets the requirements, and as-built drawings formed by the general project contractor or the contractors of design, procurement, construction and testing during the implementation of the construction project and handed over to the development organization during the project handover, which is an integral part of the filing of construction project documentations
3.2
original quality certificate
product quality certificate affixed with a special seal for inspection of manufacture or quality certificate or a continuous quality certificate affixed with a confirmation seal on a copy of the product quality certificate by the supplier or procurement organization
3.3
project management contractor
project management enterprise that provides project management services and undertakes corresponding management responsibilities for each stage of project implementation on behalf of the development organization, as agreed by the contract and authorized by the development organization, or the project management organization established with the approval of the development organization (including project management organizations under project management modes such as PM, PMC and IPMT)
3.4
as-built drawings
drawing that truly reflects the construction results of construction projects