1 Scope
This standard gives practical guidance on conducting risk assessment for machinery in accordance with GB/T 15706-2012 and describes various methods and tools for each step in the process.
This standard gives examples of different measures that can be used to reduce risk and is intended to be used for risk assessment on a wide variety of machinery in terms of complexity and potential for harm.
Its intended users are those involved in the design, installation or modification of machinery (for example, designers, technicians or safety specialists).
Appendix A provides a specific example for a risk assessment and a risk reduction process.
2 Normative References
The following documents for the application of this document are essential. Any dated reference, just dated edition applies to this document. For undated references, the latest edition (including any amendments) applies to this document.
GB/T 15706-2012 Safety of Machinery - General Principles for Design - Risk Assessment and Risk Reduction (ISO 12100: 2010, IDT)
3 Terminologies and Definitions
For the purposes of this standard, the terminologies and definitions given in GB/T 15706-2012 and the following apply.
3.1
Manufacturer
Supplier
Entity (for example, designer, manufacturer, contractor, installer, integrator) who provides equipment or services associated with machinery or parts of machinery.
Note: A user can also act in the capacity of a supplier to himself.
4 Preparation for Risk Assessment
Contents
Foreword i
Introduction iii
1 Scope
2 Normative References
3 Terminologies and Definitions
4 Preparation for Risk Assessment
4.1 General
4.2 Using the Team Approach for Risk Assessment
5 Risk Assessment Process
5.1 General
5.2 Determination of the Limits of the Machinery
5.3 Hazard Identification
5.4 Risk Estimation
6 Risk Estimation Tools
6.1 General
6.2 Risk Matrix
6.3 Risk Graph
6.4 Numerical Scoring
6.5 Hybrid Tool
7 Risk Evaluation
8 Risk Reduction
8.1 General
8.2 Inherently Safe Design
8.3 Safeguarding and/or Complementary Protective Measures
8.4 Information for Use
8.5 Standard Operating Procedures
9 Risk Assessment Iteration
10 Documentation of Risk Assessment.
Appendix A (Informative) Example Application of the Process of Risk Assessment and Risk Reduction
Bibliography