This code is applicable to the inspection before commissioning I&C system of the ash and slag, the commissioning before and after start up as well as the commissioning acceptance check in the construction, extension and renovation engineering with unit rated capacity of or above 200MW in power plant. As for the thermal generator set with unit rated capacity bellow 200MW, the commissioning of the I&C system of ash and slag may also be implemented by referring to code.
Foreword
1 Scope
2 Normative Reference
3 Definitions
4 Preparation before Commissioning the I&C System of Ash and Slag
5 Commissioning of I&C System of Ash and Slag before Start up
6 Commissioning of I&C System of Ash and Slag after Start up
7 Commissioning Acceptance of I&C System of Ash and Slag
Annex A
Annex B