1.0.1 This Standard was formulated for the purpose of guaranteeing the quality of anti-corrosion of shaft equipment in coal mine (hereinafter referred to as shaft equipment), extending its service life, reducing the loss caused by corrosion and unifying the technical requirements in the processes of anti-corrosion design, construction, inspection and acceptance.
1.0.2 This Standard is applicable to the anti-corrosion design, construction, inspection and acceptance of shaft equipment newly constructed, extended and reconstructed as well as maintained. The anti-corrosion process of steel structure head-frame (tower), pipeline and other steel members in coal mine may be implemented according to this Standard.
1.0.3 Anti-corrosion measures or corrosion-resistant materials shall be adopted for shaft equipment.
1.0.4 The anti-corrosion for shaft equipment shall be implemented practically, designed rationally, constructed normatively, and inspected and accepted strictly.
1.0.5 The following documents are indispensable for the application of this Standard. For dated references, only the dated edition is applicable to this document. For undated references, the latest editions of the normative documents (including all the amendments) are applicable to this document.
1 General 1
2 Terms 3
3 Design 5
3.1 General Provisions 5
3.2 Surface Preparation 5
3.3 Thermal Spraying Metallic Coating and Hot-dip Galvanizing Coating 6
3.4 Protective Paint Coating 6
3.5 FRP Composite 6
4 Construction 8
4.1 General Provisions 8
4.2 Surface Preparation 9
4.3 Thermal Spraying Metallic Coating and Hot-dip Galvanizing Coating 10
4.4 Protective Paint Coating 11
4.5 Anti-corrosion Maintenance, Repair 11
5 Inspection and Acceptance 13
5.1 General Provisions 13
5.2 Surface Preparation 13
5.3 Thermally Spraying Metallic Coating and Hot-dip Galvanizing Coating 13
5.4 Protective Paint Coating 14
Appendix A Anti-corrosion Coating System Design Commonly Applied to Shaft Equipment 15
Appendix B Protective Paints and Corrosion-resistant Materials Commonly Applied to Shaft Equipment 19
Appendix C Metal Surface Preparation Levels 21
Explanation about Standard 22