This standard establishes general principles for the design of I&C laboratory in the fuel electric plant.
This standard is applicable to the new or extension of fuel electric plant with the single unit capacity from 125MW to 600 MW. For the fossil fuel power plant with other single unit capacity (below 125MW or above 600MW), their laboratory area and the disposal of standard measuring instrument and equipment can refer to this standard.
Foreword II
1 Scope
2. Normative Reference
3 Terms and Definitions
4 Arrangement and area of I&C laboratory
4.1 Functions of I&C laboratory
4.2 Arrangement of I&C laboratory
4.3 Area of I&C laboratory
5 Basic Requirements of I&C Laboratory
5.1 Arrangement of I&C Laboratory
5.2 Environmental requirements of I&C Laboratory
5.3 Power Positioning and Earthing of I&C Laboratory
6 Standard Measuring Instrument and Equipment of I&C Laboratory
6.1 Basic Requirements on the Arrangement of Standard Measuring Instrument and Equipment
6.2 Technical Requirements of Standard Measuring Instrument and Equipment
Annex A